What is the Delivery time of a Lift?
Once you have ordered the model of lift you want, SWIFT’s delivery time typically ranges from 6 to 10 weeks, depending on the model, customization options, and location. During this period, your lift is carefully manufactured, tested, and packed for secure transport.
The actual lift installation itself is quick and efficient, usually taking just 3 to 5 days, provided that all site preparations have been completed in advance. Our experienced technicians work to ensure the lift is installed to the highest standards with minimal disruption to your home. If any structural adjustments are required before installation, this may affect the overall project timeline.
SWIFT’s delivery time reflects both our commitment to quality and our streamlined logistics process. We coordinate closely with homeowners, builders, and architects to make sure every stage — from production to final installation — runs as smoothly and quickly as possible.